I have a question for those that run NXStage CRRT regarding documentation. I’ve ran CRRT with nxstage for about 8 Years, at this new facility how I was taught to document makes absolutely zero sense to me. I reached out to the educator and asked how I should be documenting. It is totally different from how the nurses are documenting on the floor.
The nurses on the floor still use paper, do hand calculations and don’t even update the totals into the EMR. I am not use to paper so I get my totals from the EMR and document my pressures Into the EMR.
The main problem is the CRRT totals for the hours (Pressures and total removed from the machine) the floor nurses document on a totally different hour from the machine.
So eg. I start the machine at 2131, the totals for 2131-2200 (which is actually 2131 to 2159 since results pop up at the start of 2200hrs) I document under 2100 hours those results. The nurses document everything 0 from the pressures to the total removed and document those actual totals the next hour, so for that example under 2200. I can’t wrap my head around why when it is not 0, the machine clearly has the results on the screen.
Nobody, NOT ONE person can give me an answer. It’s simply the way it is.
My manager simply said he’s not use to charting in the EMR because it’s too confusing, the staff said it is also. I get it because most nurses at this facility are in their late 60s but cerner is not the difficult! It clearly tells you where to put your results!
Does anyone else chart it on a different hour? If so can you explain why.
I have a question for those that run NXStage CRRT regarding documentation. I’ve ran CRRT with nxstage for about 8 Years, at this new facility how I was taught to document makes absolutely zero sense to me. I reached out to the educator and asked how I should be documenting. It is totally different from how the nurses are documenting on the floor.
The nurses on the floor still use paper, do hand calculations and don’t even update the totals into the EMR. I am not use to paper so I get my totals from the EMR and document my pressures Into the EMR.
The main problem is the CRRT totals for the hours (Pressures and total removed from the machine) the floor nurses document on a totally different hour from the machine.
So eg. I start the machine at 2131, the totals for 2131-2200 (which is actually 2131 to 2159 since results pop up at the start of 2200hrs) I document under 2100 hours those results. The nurses document everything 0 from the pressures to the total removed and document those actual totals the next hour, so for that example under 2200. I can’t wrap my head around why when it is not 0, the machine clearly has the results on the screen.
Nobody, NOT ONE person can give me an answer. It’s simply the way it is.
My manager simply said he’s not use to charting in the EMR because it’s too confusing, the staff said it is also. I get it because most nurses at this facility are in their late 60s but cerner is not the difficult! It clearly tells you where to put your results!
Does anyone else chart it on a different hour? If so can you explain why.